Here are the links to all the chapters in the Draft Environmental Impact Report (DEIR) presented by Kilroy to the City. The comment period ends on May 14, 2012 extended to May 29, 2012, a 60 day review period.
|
Please send your written comments to the following address (mention "ONE PASEO, Project No. 193036/SCH No. 2010051073") Martha Blake, Environmental Planner, City of San Diego Development Services Center, 1222 First Avenue, MS 501, San Diego, CA 92101 or e-mail your comments to DSDEAS@sandiego.gov with the subject line "ONE PASEO, Project No. 193036/SCH No. 2010051073". |
DEIR Executive Summary
Here is just the Executive Summary of the DEIR, which provides a draft overview of the findings.
Related Documents
If you're interested in the precise plan or other related documents, scroll past the DEIR files.
Here are links to the indivdual DEIR files:
These files are the actual DEIR documents, as distributed by the City. The contents of each document are listed, along with their page location within the PDF file. For instance, "p. 66 of 82" is a reference to the 66th page in the pdf file that is 82 pages long.
Note: Information on submitting a comment to the DEIR is contained in the first document, the Draft EIR Public Notice. See this document about submitting comments. Comments are due May 29, 2012.
- Draft EIR Public Notice - The review ends: May 14, 2012
- Draft EIR Part 1 of 9: Contains the DEIR Cover letter (p. 1 of 82), DEIR Cover and Table of Contents (p. 19 of 82), DEIR Executive Summary (p. 37 of 82), DEIR Section 1 - Introduction (p. 66 of 82), DEIR Section 2 - Environmental Setting (p. 73 of 82).
- Draft EIR Part 2 of 9: Contains DEIR Section 3 - Project Description (p. 1 of 15).
- Draft EIR Part 3 of 9: Contains DEIR Section 3 - Project Description, continued (p. 1 of 15).
- Draft EIR Part 4 of 9: Contains DEIR Section 4 - History of Project Changes (p. 1 of 147), DEIR Section 5 - Environmental Analysis (p. 4 of 147). Note: Environmental Analysis section 5.1 LAND USE - p. 5.
- Draft EIR Part 5 of 9: Contains DEIR Section 5 - Environmental Analysis, continued (p. 1 of 93). Note: Environmental Analysis section 5.2 TRANSPORTATION / CIRCULATION / PARKING - p. 2.
- Draft EIR Part 6 of 9: Contains DEIR Section 5 - Environmental Analysis, continued (p. 1 of 19). Note: Environmental Analysis section 5.3 VISUAL EFFECTS AND NEIGHBORHOOD CHARACTER - p. 2.
- Draft EIR Part 7 of 9: Contains DEIR Section 5 - Environmental Analysis, continued (p. 1 of 39). Note: Environmental Analysis section 5.3 VISUAL EFFECTS AND NEIGHBORHOOD CHARACTER continued - p. 2.
- Draft EIR Part 8 of 9: Contains DEIR Section 5 - Environmental Analysis, continued (p. 1 of 29). Note: Environmental Analysis section 5.4 NOISE - p. 2.
- Draft EIR Part 9 of 9: Contains DEIR Section 5 - Environmental Analysis, continued (p. 1 of 267), Note: Environmental Analysis section 5.5 AIR QUALITY - p. 2, section 5.6 ENERGY - p. 30, section 5.7 GREENHOUSE GAS EMISSIONS - p. 68, section 5.8 PALEONTOLOGICAL RESOURCES - p. 98, section 5.9 BIOLOGICAL RESOURCES - p. 106, section 5.10 HYDROLOGY / WATER QUALITY - p. 110, section 5.11 PUBLIC UTILITIES - p. 133, section 5.12 PUBLIC SERVICES AND FACILITIES / RECREATION - p. 149, section 5.13 HEALTH AND SAFETY - p. 158, section 5.14 HISTORICAL RESOURCES - p. 166. , DEIR Section 6 - Cumulative Impacts (p. 176 of 267), DEIR Section 7 - Mitigation, Monitoring, and Reporting Program (p. 190 of 267), DEIR Section 8 - Effects Found Not to be Significant (p. 209 of 267), DEIR Section 9 - Significant Environmental Effects Which Cannot Be Avoided (p. 214 of 267), DEIR Section 10 - Significant Irreversible Environmental Changes (p. 219 of 267), DEIR Section 11 - Growth Inducement (p. 222 of 267), DEIR Section 12 - Alternatives (p. 225 of 267), DEIR Section 13 - References (p. 250 of 267), DEIR Section 14 - Individuals and Organizations Consulted (p. 261 of 267), DEIR Section 15 - Certifications / Qualifications (p. 264 of 267).
- Draft EIR Apps Part 1: Appendix A - Notice of Preparation and Public Comments (p. 1 of 118), Appendix B - Retail Market Analysis (p. 72 of 118).
- Draft EIR Apps Part 2: Appendix C - Traffic Impact Analysis (p. 1 of 435), Appendix D - Shared Parking Analysis (p. 335 of 435), Appendix E - Sight Visibility Analysis (p. 395 of 435).
- Draft EIR Apps Part 3: Appendix F - Acoustical Report (p. 1 of 822), Appendix G - Air Quality and Greenhouse Gas Technical Report (p. 80 of 822).
- Draft EIR Apps Part 4: Appendix H - Drainage Study (p. 1 of 159), Appendix I - Water Quality Technical Report (p. 32 of 159), Appendix J - Water Supply Assessment and Water Supply Verification (p. 98 of 159), Appendix K - Water Study (p. 139 of 159).
- Draft EIR Apps Part 5: Appendix L - Sewer Study (p. 1 of 96), Appendix M - Waste Management Plan (p. 18 of 96).
- Draft EIR Apps Part 6: Appendix N - Phase I Environmental Site Assessment (p. 1 of 158).
- Draft EIR Apps Part 7: Appendix O - Report of Geotechnical Investigation and Existing Fill Evaluation (p. 1 of 219), Appendix P - Preliminary Geotechnical Investigation (p. 81 of 219).
Here's the new DEIR traffic appendicies:
- Traffic Appendix A
- Traffic Appendix B
- Traffic Appendix C
- Traffic Appendix D
- Traffic Appendix E
- Traffic Appendix F
- Traffic Appendix G
- Traffic Appendix H
- Traffic Appendix I
- Traffic Appendix J
- Traffic Appendix K
- Traffic Appendix L
- Traffic Appendix M
- Traffic Appendix N
- Traffic Appendix O
- Traffic Appendix P
- Traffic Appendix Q
- Traffic Appendix R
- Traffic Appendix S
- Traffic Appendix T
- Traffic Appendix U
Related Documents
The DEIR discusses amendments to the Precise Plan and the PDO. NOTE that comments to these documents get sent to a different place than the DEIR comments, in this case, to Bernie Turgeon, Senior Planner. Please read the Distribution Memo Document for complete information on commenting on the Precise Plan and PDO amendments. Comments to these documents are also due May 29, 2012.
Here are these updates:
- City of San Diego's Carmel Valley Documents Page
- Precise Plan and PDO Distribution Memo - Document that describes the process and gives information on how to comment on the proposed Community Plan Amendment.
- Carmel Valley Neighborhood 2 Precise Plan Amendment - This is the Precise Plan Amendment for the employment center, which gives detailed planning information for the project. This includes a history of the site and vision for the development, land use, mobility, design guidelines, landscape guidelines, public facilities, services and safety, and implementation details.
- Carmel Valley Planned District Ordinance (PDO) Amendment - This is a document that provides detailed information on the new land-use "zone" being created for One Paseo, which includes specifics on what can be done on the property, building heights, and other details of the development.
Official List of DEIR Documents
This is a link to the City's official list of the documents, which is impossible to use! PLEASE, scroll down on this page to find a better list of the documents, including information as to what is inside of each one!




7 Comments
No to this Density
Submitted by Robin Mars on
This spot should be built to the density allowed in the community plan. I purchased my home under this assumption and the construction should stay within the approved density of the community!!!
Sorry for the delay...
Submitted by ken on
Sorry for the delay getting your comment posted, I'm still working out the bugs in the system!
Attribution
Submitted by Anonymous on
I totally support everything you are about, and make this comment only to strengthen your influence.
I think it would lend more authority to your articles if "ken" could be fully identified. He appears to be a sole contributor, though I'm fairly sure he's not.
For the record, I live in the Torrey Pines Community at 13914 Boquita Drive (dscheffler@san.rr.com) and want to make sure that the impact on One Paseo on our side of the freeway is also recognized as considerable and unsupportable.
DS
Who is ken?
Submitted by ken on
I'm "ken", Ken Farinsky. I run the website and do much of the writing, although many of the ideas come from people involved in the group. In reality, most of the articles should probably say "What Price Main Street", because they're often a group effort.
I'll think about writing a "who we are" section for the "about" page, but I've been busy just keeping up with the stories here, the facebook page, and reading the DEIR...
Were the size and scope of
Submitted by JS on
Were the size and scope of this project to be halved, it would still be a monumentally overwhelming monstronsity for such a small community. What a nightmare! They only reason a DEIR could possibly get this far is money and politics.
one paseo
Submitted by sundar on
Hi Ken,
What's the state of this project? Is there anything more that could be done to not let this go through?
Sincerely,
sundar
project status
Submitted by ken on
The City is currently working on all the comments to the DEIR. I have requested an update, but have not yet heard back.
Add new comment